RWLR headnotes

The << links will work in the same way as your browser's Back button
unless you have opted to disable Javascripts.

8. Recording of highways

8.2: Wildlife and Countryside Act 1981 continued

Wrongly reclassified RUPPssdw.jpg (14698 bytes)

Alan Kind LL.M.

  The National Parks and Access to the Countryside Act 1949 introduced the category of Roads Used as Public Paths (RUPPs) into the classification of minor highways. In the Countryside Act 1968, however, the legislature decreed the abolition of this category and provided that all RUPPs should be reclassified. Some of them were subsequently recorded on definitive maps as footpaths, but in 1975 the Court of Appeal held that such reclassifications were inconsistent with the 1949 Act, which was interpreted as having provided that RUPPs carried at least bridleway rights. Although wider powers of reclassification were subsequently conferred by the Wildlife and Countryside Act 1981, the fact remains that many RUPPs were wrongly reclassified, prior to 1975, as having neither vehicular nor bridleway rights. Before changes can be made to the definitive map, however, legal hurdles now contained in the 1981 legislation have to be overcome. The resulting complex situation suffices to ensure that correcting the erroneous reclassifications is far from straightforward. The writer of this article puts forward an idea of his own which, if valid, would facilitate the making of such corrections for certain former RUPPs.
<<

Ex parte Cowell: case note

George Laurence Q.C.

  S.31 of the Highways Act 1980 provides that 20 years use of a way by the public, as of right and without interruption, will result in the way being deemed to have been dedicated as a highway in the absence of sufficient evidence of an intention not to dedicate. In R. v. Secretary of State for the Environment ex parte Cowell in which an attempt to upgrade certain footpaths to bridleways in reliance on s.31 was unsuccessful, the Court of Appeal discussed the approach to be adopted to cases under the section. The result also incidentally illustrates the difficulties which face those who seek to challenge a decision, made under s.53(5) of the Wildlife and Countryside Act l981, not to make a definitive map modification order.
<<

Modifications of the definitive map

George Laurence Q.C.

  After the passage of more than ten years since Part III of the Wildlife and Countryside Act came into force, it is appropriate to consider how its provisions are working in practice. This article sets out the provisions for modification of the definitive map under s.53, and for RUPP reclassifications under s.54, and considers some difficulties which can be encountered in their application. In particular it questions the role of the Secretary of State in the appeal process under paragraph 4 of schedule 14.
<<

R. v. Cornwall C.C. ex p. Huntington (C.A.)

George Laurence Q.C.

  The Wildlife and Countryside Act 1981, Schedule 15 paragraph 12(3) completely ousts any challenge to an incorrectly made modification order except during a six week period following publication of the confirmation of the order.
<<

Ex p. Bagshaw and ex p. Norton

George Laurence Q.C.

  S.53(3)(c)(i) of the Wildlife and Countryside Act 1981 provides for councils to make definitive map modification orders upon discovering evidence which, when considered with all other relevant evidence available to them, shows that a right of way
    [a] subsists or
    [b] is reasonably alleged to subsist.
The evidence necessary to satisfy [b] is less than that necessary to satisfy [a].
<<

Ex parte Kent C.C.: case note

Edwin Simpson M.A., B.C.L., Barrister, Tutor, Christ Church, Oxford

  The proper scope of the duty to modify the definitive map and statement as part of the process of continuous review has recently been considered in R. v. Secretary of State for the Environment, ex parte Kent County Council. The procedure for such modifications was held not to have been appropriately used to delete the right of way concerned; recourse should have been made to other powers under the Highways Act 1980.
<<

Definitive map - continuous review

George Laurence Q.C.

The incremental, or continuous, review procedure to keep the definitive map up to date and correct under s.53 of the Wildlife and Countryside Act 1981 appears to be working reasonably well. Questions arise as to whether it can ever be proper for those who wish a modification order to be made, to call on a surveying authority to make such an order even where no formal application has been made under s.53(5) of the Act; and also whether an authority has an obligation to comply with a direction made by the Secretary of State under paragraph 4 of Schedule 14 of the Act.
<<

R. v. SoS for Wales, ex p. Emery

D. Miller LL.M.(Cantab.), B.A., Barrister

  A case note
  The applicant, a member of the Ramblers' Association, sought to quash the decision of the Secretary of State for Wales made pursuant to his appellate powers under Schedule 14 paragraph 4(2) of the Wildlife and Countryside Act 1981 (the 1981 Act). He had refused to direct Clwyd County Council to make a modification order, affecting the definitive map and statement of its area, to show an alleged public footpath. The judge, allowing the application, ordered the decision of the Secretary of State for Wales to be quashed. He held that, where there was a substantial conflict of evidence as to whether a public right of way could reasonably be alleged to subsist within the meaning of s.53(3)(c)(i) of the 1981 Act, the Secretary of State for Wales was wrong to resolve that dispute on documentary evidence alone, and that procedural fairness, and perhaps the claimant's legitimate expectations, required a public inquiry to be held in order to allow the evidence to be tested properly.
<<

Ex parte Emery in the Court of Appeal

James Stephens M.A. (Oxon), Solicitor

  A case note
  The Court of Appeal approved the approach to the construction of s.53 of the Wildlife and Countryside Act 1981 which Owen J. had adopted in R. v. Secretary of State for the Environment ex parte Bagshaw and Norton, and held that where there is a conflict of apparently credible evidence, a right of way "is reasonably alleged to subsist" if, reasonably accepting the evidence of one side and reasonably rejecting that of the other, the right would be shown to exist. The Court rejected the view that in such cases a local inquiry should be held before determining an appeal under Schedule 14 of the 1981 Act.
<<

O'Keefe No.2 in the Court of Appeal

David Braham Q.C.

  A case note
  To quote from the judgment, Mr. and Mrs. O'Keefe "engaged in a three day hearing in this Court. On this occasion they conducted their case in person with Mr. O'Keefe as advocate, assisted by Mrs. O'Keefe in the presentation of legal arguments summarised in 106 pages of typed script. The submission appeared to be the product of years of research into the law affecting judicial review, into the complex legislation on public rights of way and into the detailed factual history of this dispute and of footpaths generally in the Isle of Wight". Nevertheless the appeal was dismissed.
<<

R. v. Wilts C.C., ex p. Nettlecombe Ltd.

Louise Davies, B.A., B.C.L. Barrister

  A case note
  The first issue in this case was the correct interpretation of the definition of a byway open to all traffic in s.66(1) of the Wildlife and Countryside Act 1981. Dyson J. decided that a way falls within the definition only if it is currently being used by the public mainly for the purposes for which footpaths and bridleways are so used. The second issue was whether the 1981 Act, and in particular paragraph 12 of Schedule 15 thereto, excluded the court's jurisdiction to grant judicial review of the Council's decision to make a modification order under s.53(2) of the Act. It was decided that the court was able to grant judicial review where there had been a plain error of law.
<<

Extra steps on the way to D.M.M.O.s

David Braham Q.C.

  The decision in R. v. Wiltshire County Council, ex parte Nettlecombe Limited establishes the need to take two steps additional to the usual statutory procedures, before making a definitive map modification order, in those cases where the way is a public carriage road which has fallen into disuse because it is blocked by undergrowth or deliberate obstructions.
<<

The transfer of parts of definitive maps

John Trevelyan, Deputy Director, Ramblers' Association

   Local government reorganisation gives rise to difficulties in administering definitive maps and statements. Various statutory provisions result in some authorities having more than one definitive map for their areas.
<<

Potential liabilities arising from surveying authority roles

George Laurence QC

Failure to keep the definitive map up to date.
The implications of using a working copy definitive map.
Mistakes on consolidated map.
Pre-contract Inquiries

 

<<